Swiftwater Solar
80 MW generation in Monroe, PA · In queue since March 2019 · Proposed COD December 2025
80 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
6y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-31
Swiftwater Solar is a proposed 80 MW solar generation project located in Monroe County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AE2-175, with a queue entry date of March 19, 2019, and a proposed commercial operation date of December 31, 2025. The interconnection agreement for the project has been executed.
The proposed project is interconnected with PPL at the Jackson-Long Pond 69 kV point of interconnection. Swiftwater Solar has been the subject of recent news coverage, including reports on regulatory and industry developments.
Generated from interconnection queue and public data sources
State
PA
County
Monroe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Jackson-Long Pond 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26