PJM-AE2-187
60 MW generation in Pittsylvania, VA · In queue since March 2019 · Proposed COD September 2020
60 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2020
Total Duration
1y 6m
Schedule
69 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-09-01
PJM-AE2-187 is a proposed 60 MW solar generation project located in Pittsylvania County, Virginia. The project is in the PJM interconnection queue, having entered on March 18, 2019. Dominion is the listed utility. The proposed commercial operation date is September 1, 2020.
The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Shockoe DP-Chatham 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-187