Kensington Solar
145 MW generation in Columbiana, OH · In queue since March 2019 · Proposed COD January 2026
145 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-01-02
Kensington Solar is a proposed 145 MW solar generation project located in Columbiana County, Ohio. The project, developed under the utility ATSI, is interconnected within the PJM Interconnection queue as entry PJM-AE2-194, with a queue entry date of March 18, 2019. The proposed commercial operation date is January 2, 2026.
The project's interconnection agreement (IA) has been executed, though its current status is listed as suspended. The point of interconnection (POI) is the Congress-Toronto 138 kV line. The Kensington Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OH
County
Columbiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Congress-Toronto 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Kensington Solar