Dover Solar
55 MW generation in York, PA · In queue since March 2019 · Proposed COD September 2027
55 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-07
Dover Solar is a proposed 55 MW solar generation project located in York County, Pennsylvania. The project is in the PJM interconnection queue as entry AE2-211, with a queue entry date of March 20, 2019, and a proposed commercial operation date of September 7, 2027. The interconnection agreement (IA) for the project has been executed.
The Dover Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Jackson-Three Mile Island 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26