Pleasant Prairie Solar Energy Center
200 MW generation in Franklin, OH · In queue since March 2019 · Proposed COD March 2027
200 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-30
The Pleasant Prairie Solar Energy Center is a proposed 200 MW solar generation project in Franklin County, Ohio. The project, developed by AEP, is currently active in the PJM interconnection queue as entry AE2-214, with a queue entry date of March 23, 2019. The proposed commercial operation date is March 30, 2027, and the Interconnection Agreement (IA) has been executed.
The Pleasant Prairie Solar Energy Center has been the subject of recent news coverage, with five articles categorized as industry and development related.
Generated from interconnection queue and public data sources
State
OH
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Cole 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COLE 34.5 KV PLEPRASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Pleasant Prairie Solar Energy Center