Sloopy Solar Energy Center
180 MW generation in Clark, OH · In queue since March 2019 · Proposed COD September 2028
180 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-09-30
The Sloopy Solar Energy Center is a proposed 180 MW solar generation project located in Clark County, Ohio. The project is in the PJM interconnection queue as entry PJM-AE2-217, with a queue entry date of March 21, 2019, and a proposed commercial operation date of September 30, 2028. The interconnection agreement (IA) has been executed.
The project is interconnected to the ATSI utility system at the East Springfield-London 138 kV point of interconnection. The Sloopy Solar Energy Center has been the subject of recent news coverage, with three articles categorized as industry and regulatory news.
Generated from interconnection queue and public data sources
State
OH
County
Clark
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
East Springfield-London 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26