Riverstart Solar Park II
125 MW generation in Randolph, IN · In queue since March 2019 · Proposed COD November 2027
125 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-11-15
Riverstart Solar Park II is a proposed 125 MW solar generation project located in Randolph County, Indiana. The project is being developed within the PJM Interconnection region and is interconnected to the Losantville 345 kV point of interconnection.
The project entered the PJM interconnection queue as queue ID PJM-AE2-220 on March 21, 2019. Its proposed commercial operation date is November 15, 2027, and the Interconnection Agreement (IA) has been executed. The transmission utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Losantville 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Riverstart Solar Park II