Maple Solar
35 MW generation in Huntington, IN · In queue since March 2019 · Proposed COD December 2028
35 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
The Maple Solar project is a proposed 35 MW solar generation facility located in Huntington County, Indiana. The project is in the PJM interconnection queue (queue ID PJM-AE2-234) as of March 22, 2019, with a proposed commercial operation date of December 31, 2028. The interconnection agreement (IA) for the project has been executed.
The proposed project is interconnected to the AEP utility grid at the Liberty Center-Buckeye Tap 69 kV point of interconnection.
Generated from interconnection queue and public data sources
State
IN
County
Huntington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Liberty Center-Buckeye Tap 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PRINTZ 18 KV GTG2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Maple Solar