CE-FILMORE
16 MW generation in Centre, PA · In queue since March 2019 · Proposed COD December 2027
16 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The CE-FILMORE project is a proposed 16 MW solar generation project located in Centre County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AE2-248, with a queue entry date of March 25, 2019. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the System Impact Study phase, but is listed as suspended. The point of interconnection is the Fillmore-Thompson Farm 46 kV substation. The utility is listed as APS.
Generated from interconnection queue and public data sources
State
PA
County
Centre
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Fillmore-Thompson Farm 46 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CE-FILMORE