Panther Grove 2
100 MW generation in Woodford, IL · In queue since March 2019 · Proposed COD January 2027
100 MW
Capacity
1
Components
Wind
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-01-18
The Panther Grove 2 project is a proposed 100 MW wind generation project located in Woodford County, Illinois. The project is in the PJM interconnection queue as entry PJM-AE2-255, with a queue entry date of March 26, 2019, and a proposed commercial operation date of January 18, 2027. The interconnection agreement for the project has been executed.
The project is located within the ComEd service territory and interconnects to the Molecreek 345 kV substation. The project has appeared in recent news coverage regarding renewable energy development in Illinois.
Generated from interconnection queue and public data sources
State
IL
County
Woodford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Molecreek 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Panther Grove 2