PJM-AE2-261
299 MW generation in Christian, IL · In queue since March 2019 · Proposed COD June 2022
299 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-06-01
The proposed PJM-AE2-261 project is a 299 MW solar generation project located in Christian County, Illinois. Interconnection is with ComEd within the PJM Interconnection queue. The project entered the queue on March 28, 2019, and has a proposed commercial operation date of June 1, 2022. Its interconnection status is currently in the System Impact Study phase.
The project consists of 299 MW of solar photovoltaic generation. The point of interconnection is the Kincaid-Pana 345 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kincaid-Pana 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-261