Woodsdale Renewable Energy Center
49 MW generation in Butler, OH · In queue since March 2019 · Proposed COD June 2026
49 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-06-01
The Woodsdale Renewable Energy Center is a proposed solar generation project located in Butler County, Ohio. The project, with a total capacity of 49 MW, is being developed within the Dayton Power & Light (DEOK) service area.
The project is listed in the PJM interconnection queue as entry AE2-267, with an original queue entry date of March 29, 2019. Its proposed commercial operation date is June 1, 2026, and the project has an Interconnection Agreement (IA) executed. The point of interconnection (POI) is the Woodsdale 345 kV substation.
Generated from interconnection queue and public data sources
State
OH
County
Butler
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DEOK
Entity
PJM
Service Type
—
Point of Interconnection
Woodsdale 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Woodsdale Renewable Energy Center