Trade Post Energy Storage
50 MW storage in Sullivan, IN · In queue since March 2019 · Proposed COD December 2028
50 MW
Capacity
1
Components
Battery
7y 2m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-31
Trade Post Energy Storage is a proposed 50 MW battery storage project located in Sullivan County, Indiana. The project is in the PJM interconnection queue as entry PJM-AE2-276, with a queue entry date of March 28, 2019, and a proposed commercial operation date of December 31, 2028. The project's interconnection agreement has been executed.
The project, which will interconnect to the Sullivan 345kV point of interconnection, is being developed within the AEP utility territory.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Sullivan 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SULLIVAN69 KV T1
- POI Substation
- Sullivan Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Trade Post Energy Storage