Nottingham Solar
100 MW generation in Harrison, OH · In queue since March 2019 · Proposed COD December 2023
100 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-12-15
Nottingham Solar is a proposed 100 MW solar generation project located in Harrison County, Ohio. The project is interconnected to the PJM grid under queue ID PJM-AE2-290, with an interconnection queue entry date of March 29, 2019. The proposed commercial operation date is December 15, 2023, and the Interconnection Agreement (IA) has been executed. The Point of Interconnection (POI) is the Nottingham 138 kV substation.
The proposed project is linked to the existing Nottingham Solar operating plant (EIA plant ID 66658). The project has appeared in recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
OH
County
Harrison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Nottingham 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STEUBENV34.5 KV STEUBNSP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26