Nottingham Solar (PJM-AE2-290) — Project Summary

Queue ID
PJM-AE2-290
Capacity
100 MW
Technology
Solar
Status
active
Location
Harrison, OH
Region
PJM
Developer
IA Status
IA Executed

Nottingham Solar

PJM-AE2-290BetaActiveSolarPJMLBNL + Live

100 MW generation in Harrison, OH · In queue since March 2019 · Proposed COD December 2023

100 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection

Total Duration

4y 9m

Schedule

29 months past proposed COD

Construction75%
Queue EntryMar 29, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-12-15

About

Nottingham Solar is a proposed 100 MW solar generation project located in Harrison County, Ohio. The project is interconnected to the PJM grid under queue ID PJM-AE2-290, with an interconnection queue entry date of March 29, 2019. The proposed commercial operation date is December 15, 2023, and the Interconnection Agreement (IA) has been executed. The Point of Interconnection (POI) is the Nottingham 138 kV substation.

The proposed project is linked to the existing Nottingham Solar operating plant (EIA plant ID 66658). The project has appeared in recent news coverage related to regulatory matters.

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Harrison

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Nottingham 138 kV

Data Source

LBNL + Live

ApplicantWild Grains Solar, LLC; Nottingham Solar LLC±Farm and Dairy · 2022-08-25
AgencyOhio Power Siting BoardFarm and Dairy · 2022-08-25
RulingApproval±Farm and Dairy · 2022-08-25
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
STEUBENV34.5 KV STEUBNSP

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Nottingham Solar