PJM-AE2-291
102 MW generation in Pittsylvania, VA · In queue since March 2019 · Proposed COD April 2021
102 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2021
Total Duration
2y 1m
Schedule
62 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-04-01
PJM-AE2-291 is a proposed 102 MW solar generation project located in Pittsylvania County, Virginia. The project is in the PJM interconnection queue, having entered on March 29, 2019, with a proposed commercial operation date of April 1, 2021. The interconnecting utility is Dominion.
The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Grit DP-Perth 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-291