White Trillium
49.9 MW generation in Van Wert, OH · In queue since March 2019 · Proposed COD December 2027
49.9 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-30
The White Trillium project is a proposed 49.9 MW solar generation project located in Van Wert County, Ohio. The project is in the PJM interconnection queue as entry PJM-AE2-298, with a queue entry date of March 22, 2019, and a proposed commercial operation date of December 30, 2027. The interconnecting utility is AEP, and the project's interconnection agreement has been executed.
The project is listed in the PJM queue and consists of 49.9 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
OH
County
Van Wert
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Cavett Switch - West Van Wert 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about White Trillium