Squab Solar
90 MW generation in Jefferson, PA · In queue since March 2019 · Proposed COD December 2027
90 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
Squab Solar is a proposed 90 MW solar generation project located in Jefferson County, Pennsylvania. The project, under development in the PJM Interconnection queue as entry PJM-AE2-316, has an interconnection agreement executed. The queue entry date is March 30, 2019, with a proposed commercial operation date of December 31, 2027. The point of interconnection is the Brookville-Squab Hollow 138 kV line, and the interconnecting utility is PENELEC.
The Squab Solar project has been the subject of recent news coverage related to development and regulatory matters.
Generated from interconnection queue and public data sources
State
PA
County
Jefferson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Brookville-Squab Hollow 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Squab Solar