PJM-AE2-325
52.2 MW storage in Van Buren, MI · In queue since March 2019 · Proposed COD December 2022
52.2 MW
Capacity
1
Components
Battery
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AE2-325 is a proposed energy storage project located in Van Buren County, Michigan. The project, with a total capacity of 52.2 MW, consists entirely of battery storage. It is listed in the PJM interconnection queue as of March 30, 2019, with a proposed commercial operation date of December 1, 2022. The interconnection request is currently in the System Impact Study phase.
The project is interconnected to the AEP utility system at the Valley 138 kV point of interconnection.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Valley 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BEAV DUQ22 KV UNIT2
- POI Substation
- Beaver Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-325