Wythe County Solar Project
52.2 MW storage in Wythe, VA · In queue since March 2019 · Proposed COD June 2027
52.2 MW
Capacity
1
Components
Battery
7y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-15
The Wythe County Solar Project is a proposed 52.2 MW battery storage project located in Wythe County, Virginia. The project is in the PJM interconnection queue as entry AE2-326, with a queue entry date of March 30, 2019, and a proposed commercial operation date of June 15, 2027. The project's interconnection status is currently in the Facility Study phase.
The project is being developed within the AEP utility territory. Recent news coverage indicates interest in the project, with six articles appearing in the news, covering regulatory, deal-making, and industry aspects.
Generated from interconnection queue and public data sources
State
VA
County
Wythe
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Jacksons Ferry 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- JACKSONS34.5 KV WYTHECSP
- POI Substation
- Jacksons Ferry Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26