Bedington Energy Facility
100 MW generation in Frederick, MD · In queue since April 2019 · Proposed COD October 2025
100 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2025-10-31
The Bedington Energy Facility is a proposed 100 MW solar generation project located in Frederick County, Maryland. The project is being developed within the PJM Interconnection queue under queue ID PJM-AE2-333. Its queue entry date was April 1, 2019, with a proposed commercial operation date of October 31, 2025. The project has an Interconnection Agreement (IA) executed and is currently listed as suspended.
The proposed project is interconnected to the APS utility grid at the Bedington 138 kV point of interconnection. Recent news coverage has discussed the development of the Bedington Energy Facility.
Generated from interconnection queue and public data sources
State
MD
County
Frederick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Bedington 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BEDINGTO34.5 KV BEDINGSP
- POI Substation
- Bedington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.