Grassy Plains
40 MW generation in Fayette, KY · In queue since March 2019 · Proposed COD June 2027
40 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-30
The Grassy Plains project is a proposed 40 MW solar generation facility in Fayette County, Kentucky. The project is being developed within the PJM Interconnection queue as project number PJM-AE2-339. The project entered the queue on March 31, 2019, and has a proposed commercial operation date of June 30, 2027.
The project has an Interconnection Agreement (IA) that has been executed. The designated point of interconnection (POI) for the project is the Avon 138 kV substation. The transmission utility is EKPC.
Generated from interconnection queue and public data sources
State
KY
County
Fayette
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Avon 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AVONLAK2138 KV 800_B
- POI Substation
- Avon Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.