Grassy Plains (PJM-AE2-339) — Project Summary

Queue ID
PJM-AE2-339
Capacity
40 MW
Technology
Solar
Status
active
Location
Fayette, KY
Region
PJM
Developer
IA Status
IA Executed

Grassy Plains

PJM-AE2-339BetaActiveSolarPJMLBNL + Live

40 MW generation in Fayette, KY · In queue since March 2019 · Proposed COD June 2027

40 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection

Total Duration

8y 3m

Construction75%
Queue EntryMar 31, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-06-30

About

The Grassy Plains project is a proposed 40 MW solar generation facility in Fayette County, Kentucky. The project is being developed within the PJM Interconnection queue as project number PJM-AE2-339. The project entered the queue on March 31, 2019, and has a proposed commercial operation date of June 30, 2027.

The project has an Interconnection Agreement (IA) that has been executed. The designated point of interconnection (POI) for the project is the Avon 138 kV substation. The transmission utility is EKPC.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Fayette

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

EKPC

Entity

PJM

Service Type

Point of Interconnection

Avon 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
AVONLAK2138 KV 800_B
POI Substation
Avon Lake Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Grassy Plains