PJM-AE2-341
150 MW generation in Kendall, IL · In queue since March 2019 · Proposed COD December 2022
150 MW
Capacity
1
Components
Solar
7y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AE2-341 is a proposed solar generation project with a total capacity of 150 MW, located in Kendall County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 31, 2019. Its proposed commercial operation date is December 1, 2022. The project is currently in the System Impact Study phase of the interconnection process.
The proposed project is located within the ComEd utility territory and connects to the Sandwich-Plano 138 kV point of interconnection. The project consists of 150 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Sandwich-Plano 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AE2-341