Woodstock Solar
40 MW generation in Champaign, OH · In queue since March 2019 · Proposed COD July 2026
40 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-07-06
The Woodstock Solar project is a proposed 40 MW solar generation project located in Champaign County, Ohio. The project is in the PJM interconnection queue as entry AE2-342, with a queue entry date of March 31, 2019. Its proposed commercial operation date is July 6, 2026. The project's interconnection agreement has been executed.
The project, which will interconnect to the Dayton utility grid at the Woodstock 69 kV point of interconnection, is currently listed as suspended in the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Champaign
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Woodstock 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- THOMPSCR13 KV TX2
- POI Substation
- Woodstock Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Woodstock Solar