Granite Hill Solar
70 MW generation in Adams, PA · In queue since March 2019 · Proposed COD February 2026
70 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-02-01
Granite Hill Solar is a proposed 70 MW solar generation project located in Adams County, Pennsylvania. The project is listed in the PJM interconnection queue as entry AE2-345, with a queue entry date of March 13, 2019. The proposed commercial operation date is February 1, 2026. The project's interconnection agreement has been executed, but its current status is listed as suspended.
The proposed project is being developed within the PJM service territory. The point of interconnection is the Hunterstown-Texas Eastern Tap 115 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Hunterstown-Texas Eastern Tap 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Granite Hill Solar