Maryland Offshore Wind Energy Project (MOWEP)
7.3 MW generation in Sussex, DE · In queue since April 2019 · Proposed COD December 2027
7.3 MW
Capacity
1
Components
Offshore Wind
7y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 36–60 months
Proposed COD: 2027-12-31
The Maryland Offshore Wind Energy Project (MOWEP), queue ID PJM-AF1-007, is a proposed 7.3 MW offshore wind generation project located in Sussex County, Delaware. The project was entered into the PJM interconnection queue on April 1, 2019, with a proposed commercial operation date of December 31, 2027. The designated utility is DPL, and the point of interconnection is the Indian River 230 kV I substation. The project's interconnection agreement (IA) has been executed, and its current status is suspended.
The development project consists of a single 7.3 MW offshore wind component. Recent news coverage has discussed the project's progress and potential impact on the region's energy landscape.
Generated from interconnection queue and public data sources
State
DE
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Indian River 230 kV I
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- INDIANRI13 KV UNIT10
- POI Substation
- Indian River South Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.