Walnut Solar I
19.9 MW generation in King And Queen, VA · In queue since April 2019 · Proposed COD July 2026
19.9 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-14
The Walnut Solar I project is a proposed 19.9 MW solar generation project located in King and Queen County, Virginia. The project is in the PJM interconnection queue as entry PJM-AF1-014, with a queue entry date of April 4, 2019, and a proposed commercial operation date of July 14, 2026. The interconnecting utility is Dominion.
The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Harmony Village-Shackleford 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- HARMONY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.