Prospect Power (PJM-AF1-028) — Project Summary

Queue ID
PJM-AF1-028
Capacity
200 MW
Technology
Battery
Status
active
Location
Rockingham, VA
Region
PJM
Developer
IA Status
IA Executed

Prospect Power

PJM-AF1-028BetaActiveBatteryPJMLBNL + Live

200 MW storage in Rockingham, VA · In queue since May 2019 · Proposed COD February 2026

200 MW

Capacity

1

Components

Battery

7 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

6y 9m

Schedule

3 months past proposed COD

Construction75%
Queue EntryMay 13, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-02-01

About

Prospect Power is a proposed 200 MW battery storage project located in Rockingham County, Virginia. The project is being developed within the PJM Interconnection queue under queue ID PJM-AF1-028. Its queue entry date is May 13, 2019, and the proposed commercial operation date is February 1, 2026. The interconnection agreement for Prospect Power has been executed.

The project is interconnected to the Dominion utility grid at the Endless Caverns 115 kV point of interconnection. Prospect Power has been the subject of recent news coverage, with eight articles focusing on deals, regulatory matters, and development aspects of the project.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Rockingham

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Endless Caverns 115 kV

Data Source

LBNL + Live

DeveloperSwift Current EnergyEnergy Global · 2026-01-16
TransactionAcquisitionEnergy Global · 2026-01-16
OfftakerElevate RenewablesEnergy Global · 2026-01-16
PPA structurePhysicalEnergy Global · 2026-01-16
PPA term15 yearsEnergy Global · 2026-01-16
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
ENDCAVRN35 KV ENDCA1SP
POI Substation
Endless Caverns Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (3)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Prospect Power