Mt Olive Creek Solar
60 MW generation in Russell, KY · In queue since June 2019 · Proposed COD September 2026
60 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-09-30
The Mt Olive Creek Solar project is a proposed 60 MW solar generation project located in Russell County, Kentucky. The project is in the PJM interconnection queue as entry PJM-AF1-038, with a queue entry date of June 8, 2019, and a proposed commercial operation date of September 30, 2026. The interconnecting utility is EKPC.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Sewellton Jct-Webbs Crossroads 69 kV line. The developer is not specified in the provided data.
Generated from interconnection queue and public data sources
State
KY
County
Russell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Sewellton Jct-Webbs Crossroads 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Mt Olive Creek Solar