Momentum Gratz
20 MW storage in Dauphin, PA · In queue since June 2019 · Proposed COD September 2024
20 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 6–18 months
Proposed COD: 2024-09-06
The Momentum Gratz project is a proposed 20 MW battery storage project located in Dauphin County, Pennsylvania. The project is interconnected within the PJM Interconnection queue as entry PJM-AF1-040, with a queue entry date of June 15, 2019. The proposed commercial operation date is September 6, 2024, and the interconnection agreement has been executed.
The project, which is connected to the Gratz Tap 69 kV, is currently listed as suspended. The project is within the PPL utility territory.
Generated from interconnection queue and public data sources
State
PA
County
Dauphin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Gratz Tap 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.