Clermont County Solar Project
52.2 MW storage in Clermont, OH · In queue since June 2019 · Proposed COD December 2025
52.2 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 6–18 months
Proposed COD: 2025-12-31
The Clermont County Solar Project is a proposed 52.2 MW battery storage project located in Clermont County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF1-045, with a queue entry date of June 29, 2019, and a proposed commercial operation date of December 31, 2025. The project's interconnection agreement has been executed. The point of interconnection is the Cedarville-Ford 138 kV line.
The development project is listed in the queue as a storage project, with the listed technology as Battery. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
OH
County
Clermont
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DEOK
Entity
PJM
Service Type
—
Point of Interconnection
Cedarville-Ford 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26