Berry Hill (PJM-AF1-049) — Project Summary

Queue ID
PJM-AF1-049
Capacity
125 MW
Technology
Solar
Status
active
Location
Pittsylvania, VA
Region
PJM
Developer
IA Status
IA Executed

Berry Hill

PJM-AF1-049BetaActiveSolarPJMLBNL + Live

125 MW generation in Pittsylvania, VA · In queue since July 2019 · Proposed COD March 2027

125 MW

Capacity

1

Components

Solar

6y 10m

In Queue

IA Executed

IA Status

COD target: 2027

Status
Latest milestoneconstruction imminentCardinal News · 2025-11-13
Expected CODQ1 2028Cardinal News · 2025-11-13
Interconnection

Total Duration

7y 8m

Construction75%
Queue EntryJul 12, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-03-30

About

The Berry Hill proposed project is a 125 MW solar generation facility located in Pittsylvania County, Virginia. The project is in the PJM interconnection queue as entry PJM-AF1-049, with a queue entry date of July 12, 2019, and a proposed commercial operation date of March 30, 2027. The interconnecting utility is AEP. The project's interconnection agreement has been executed.

The Berry Hill development project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Pittsylvania

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Berry Hill 138 kV

Data Source

LBNL + Live

DeveloperMicroporousCardinal News · 2025-11-13
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Berry Hill