Horseshoe Bend Solar
60 MW generation in Green, KY · In queue since July 2019 · Proposed COD November 2026
60 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-30
Horseshoe Bend Solar is a proposed 60 MW solar generation project located in Green County, Kentucky. The developer is not specified in the data. The project is in the PJM interconnection queue as entry AF1-050, with a queue entry date of July 14, 2019, and a proposed commercial operation date of November 30, 2026. The interconnection agreement has been executed.
The project is interconnected to the Summer Shade - Green County 161 kV point of interconnection. Horseshoe Bend Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
KY
County
Green
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Summer Shade - Green County 161 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesNo ask pi reports yet for this entity.
ask pi about Horseshoe Bend Solar