Dover Solar
20 MW generation in York, PA · In queue since July 2019 · Proposed COD October 2026
20 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-10-14
Dover Solar is a proposed 20 MW solar generation project located in York County, Pennsylvania. The project is listed in the PJM interconnection queue as entry PJM-AF1-057, with a queue entry date of July 31, 2019. The proposed commercial operation date is October 14, 2026, and the project's interconnection agreement has been executed.
The Dover Solar project is being developed within the PJM service territory. The point of interconnection is the Jackson-Three Mile Island 230 kV II line.
Generated from interconnection queue and public data sources
State
PA
County
York
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
Jackson-Three Mile Island 230 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dover Solar