Juliet Energy
50 MW generation in Wood, OH · In queue since July 2019 · Proposed COD May 2027
50 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-05-29
The Juliet Energy project is a proposed 50 MW solar generation project located in Wood County, Ohio. The project is interconnected to the PJM grid via the ATSI utility at the Weston 69 kV point of interconnection. It entered the PJM interconnection queue (queue ID PJM-AF1-064) on July 31, 2019, and has a proposed commercial operation date of May 29, 2027. The interconnection agreement (IA) for the project has been executed.
The Juliet Energy project is linked to the existing Juliet Energy Project, LLC operating plant (EIA plant ID 68938). Recent news coverage indicates activity related to the project's development and regulatory status.
Generated from interconnection queue and public data sources
State
OH
County
Wood
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Weston 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SANDRIDG34.5 KV JULIETSP
- POI Substation
- Future Sand Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.