Cassius Blue Solar
94 MW hybrid in Sussex, VA · In queue since August 2019 · Proposed COD August 2031
94 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2031
Total Duration
12 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2031-08-01
The Cassius Blue Solar project is a proposed 94 MW solar and battery hybrid development in Sussex County, Virginia. The project consists of 94 MW of solar generation. It is located within the Dominion service area and is interconnected to the PJM Interconnection queue as project PJM-AF1-069. The project entered the queue on August 9, 2019, and has a proposed commercial operation date of August 1, 2031. The project's Interconnection Agreement (IA) has been executed.
The proposed project is interconnected at the Carson-Rogers Rd 500 kV point of interconnection. The developer is unknown. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Carson-Rogers Rd 500 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.