PJM-AF1-071
18 MW generation in Preble, OH · In queue since August 2019 · Proposed COD April 2028
18 MW
Capacity
1
Components
Solar
6y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
PJM-AF1-071 is a proposed solar generation project located in Preble County, Ohio, with a total capacity of 18 MW. The project is being developed within the PJM Interconnection queue, with an entry date of August 13, 2019. The proposed commercial operation date is April 1, 2028. The project's interconnection status is currently in the Facility Study phase. The interconnecting utility is AEP, and the point of interconnection is the College Corner 138 kV substation.
The development project consists of 18 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Preble
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
College Corner 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- AEP College Corner Substation