Murch Solar
85 MW generation in Van Buren, MI · In queue since August 2019 · Proposed COD January 2027
85 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-15
The Murch Solar project is a proposed 85 MW solar generation facility located in Van Buren County, Michigan. The project is being developed within the PJM Interconnection region and has an Interconnection Agreement (IA) executed. Its queue ID is PJM-AF1-084, with an original queue entry date of August 30, 2019, and a proposed commercial operation date of January 15, 2027.
The project is interconnected to the Hartford-Almena 69 kV point of interconnection and has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hartford-Almena 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.