Rogue's Wind
109.9 MW generation in Clearfield, PA · In queue since August 2019 · Proposed COD September 2026
109.9 MW
Capacity
1
Components
Wind
6y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-09-01
Rogue's Wind is a proposed wind generation project with a total capacity of 109.9 MW, located in Clearfield County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-086, with a queue entry date of August 30, 2019, and a proposed commercial operation date of September 1, 2026. The interconnection agreement (IA) has been executed.
The project, which interconnects to PENELEC via the Madera-Westover South 115 kV point of interconnection, has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Madera-Westover South 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rogue's Wind