Jackson Center Solar II
20 MW generation in Mercer, PA · In queue since August 2019 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-31
The Jackson Center Solar II project is a proposed 20 MW solar generation project located in Mercer County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-093, with a queue entry date of August 31, 2019, and a proposed commercial operation date of July 31, 2026. The interconnecting utility is ATSI.
The project's interconnection agreement has been executed. It has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Mercer
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Henderson-Stoneboro 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Jackson Center Solar II