Franklin Solar
20 MW generation in Crawford, PA · In queue since August 2019 · Proposed COD September 2026
20 MW
Capacity
1
Components
Solar
6y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-09-20
The proposed Franklin Solar project is a 20 MW solar generation project located in Crawford County, Pennsylvania. It is being developed within the PJM Interconnection queue as project number PJM-AF1-094. The project entered the queue on August 30, 2019, and has a proposed commercial operation date of September 20, 2026. The interconnection agreement (IA) for the project has been executed.
The project is interconnected to the PENELEC utility grid at the Union City-Cambridge Springs 34.5 kV point of interconnection. The developer is listed as PJM. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Union City-Cambridge Springs 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Franklin Solar