Gibson Solar I
100 MW generation in King George, VA · In queue since September 2019 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-12-31
Gibson Solar I is a proposed 100 MW solar generation project located in King George County, Virginia. The project, under development within the Dominion service area, is interconnected to the PJM grid at the Oak Grove-Dahlgren 230 kV point of interconnection. It entered the PJM interconnection queue (queue ID PJM-AF1-114) on September 12, 2019, and has a proposed commercial operation date of December 31, 2027. The project's Interconnection Agreement (IA) has been executed.
The Gibson Solar I project has been the subject of recent news coverage, with at least seven articles appearing in industry and deals-related publications.
Generated from interconnection queue and public data sources
State
VA
County
King George
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Oak Grove-Dahlgren 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Gibson Solar I