PJM-AF1-116
120 MW generation in Washington, KY · In queue since September 2019 · Proposed COD December 2023
120 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
4y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-29
PJM-AF1-116 is a proposed solar generation project located in Washington County, Kentucky, within the PJM Interconnection region. The project, with a total capacity of 120 MW, is being developed in the East Kentucky Power Cooperative (EKPC) service area. It consists of 120 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on September 12, 2019, and has a proposed commercial operation date of December 29, 2023. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Marion County 161 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Marion County 161 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.