Martin County Solar Project
177 MW generation in Martin, KY · In queue since September 2019 · Proposed COD December 2028
177 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2028-12-15
The Martin County Solar Project is a proposed 177 MW solar generation project located in Martin County, Kentucky. The developer is not specified in the data. This project is in the PJM interconnection queue as entry PJM-AF1-130, with a queue entry date of September 20, 2019, and a proposed commercial operation date of December 15, 2028. The interconnection agreement (IA) has been executed, but the project status is currently listed as suspended. The point of interconnection (POI) is the Inez 138 kV substation.
The project is linked to the existing Martin County Solar Project, LLC operating plant (EIA plant ID 66646). Recent news coverage relating to the project includes topics such as industry, development, and grid infrastructure.
Generated from interconnection queue and public data sources
State
KY
County
Martin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Inez 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- INEZ 34.5 KV MARTC2SP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26