CL-Green Acres
20 MW generation in Clearfield, PA · In queue since September 2019 · Proposed COD December 2027
20 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The CL-Green Acres project is a proposed 20 MW solar generation project located in Clearfield County, Pennsylvania. The project is in the PJM interconnection queue as entry AF1-134, with a queue entry date of September 19, 2019. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Philipsburg-Madera 34.5 kV line. The interconnecting utility is PENELEC. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Philipsburg-Madera 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CL-Green Acres