BL-Diamond Bear Rocks
16.3 MW generation in Adams, PA · In queue since September 2019 · Proposed COD December 2026
16.3 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The BL-Diamond Bear Rocks project is a proposed solar generation project with a total capacity of 16.3 MW, located in Adams County, Pennsylvania. The project is in the PJM interconnection queue as entry PJM-AF1-140, with a queue entry date of September 19, 2019. The proposed commercial operation date is December 31, 2026.
The project's interconnection status is currently in the System Impact Study phase. The designated point of interconnection (POI) is the Claysburg 23 kV substation. The utility is PENELEC. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
PA
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Claysburg 23 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CLAYSBUR23 KV BEARROSP
- POI Substation
- Claysburg Substation