Rockdale Solar
100 MW generation in Somerset, PA · In queue since September 2019 · Proposed COD December 2028
100 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
The Rockdale Solar project is a proposed 100 MW solar generation facility in Somerset County, Pennsylvania. The project is located within the PJM Interconnection region and is being developed as a standalone solar facility.
The project entered the PJM interconnection queue as queue ID PJM-AF1-143 on September 18, 2019, with a proposed commercial operation date of December 31, 2028. The project's interconnection agreement has been executed. Rockdale Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Lick Run 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LICKRUN 25 KV CASSELWF
- POI Substation
- Lick Run Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.