100 MW storage in Martin, KY · In queue since September 2019 · Proposed COD May 2028
100 MW
Capacity
1
Components
Battery
6y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-31
PJM-AF1-162 is a proposed 100 MW battery storage project located in Martin County, Kentucky. The project is in the PJM interconnection queue, having entered on September 20, 2019. The proposed commercial operation date is May 31, 2028. The interconnecting utility is AEP.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Inez 138 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
Martin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Inez 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- INEZ 34.5 KV MARTC2SP
- POI Substation
- Inez Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.