PJM-AF1-176
300 MW hybrid in St. Joseph, MI · In queue since September 2019 · Proposed COD October 2022
300 MW
Capacity
1
Components
Solar
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2022
Total Duration
3y 1m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
PJM-AF1-176 is a proposed 300 MW hybrid solar and battery project located in St. Joseph County, Michigan. The project, which interconnects to the PJM Interconnection queue, consists of 300 MW of solar capacity. Its queue entry date is September 25, 2019, with a proposed commercial operation date of October 31, 2022. The interconnection utility is AEP.
The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
MI
County
St. Joseph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Corey 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COREY 34 KV 1T
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-176