PJM-AF1-202
200 MW generation in Blackford, IN · In queue since September 2019 · Proposed COD September 2026
200 MW
Capacity
1
Components
Wind
6y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
7 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-15
The proposed PJM-AF1-202 project is a 200 MW wind generation facility located in Blackford County, Indiana. The project, which consists of 200 MW of wind capacity, is in the PJM interconnection queue as of September 25, 2019. The proposed commercial operation date is September 15, 2026.
The interconnection utility is AEP, and the point of interconnection is the Keystone-Desoto 345 kV line. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Keystone-Desoto 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AF1-202