CG Fulton County
199 MW generation in Fulton, OH · In queue since September 2019 · Proposed COD May 2028
199 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-31
The CG Fulton County project is a proposed 199 MW solar generation project located in Fulton County, Ohio. The project is in the PJM interconnection queue as entry PJM-AF1-206, with a queue entry date of September 26, 2019, and a proposed commercial operation date of May 31, 2028. The interconnecting utility is ATSI. The project's interconnection agreement has been executed.
The CG Fulton County project has been the subject of recent news coverage, with seven articles categorized as regulatory news.
Generated from interconnection queue and public data sources
State
OH
County
Fulton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
East Fayette 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- E_FAYET 34.5 KV ARCHESP
- POI Substation
- East Fayette Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26